Fiber Optic or Coaxial Cable Exemption

Ready to get your tax abatement for fiber optic or coaxial cable exemption?

First, thank you for participating in Montana’s commitment to prosperity and growth, one aspect of which is providing accessible and affordable broadband to our citizens. 

Some things to know as you begin this process:

Requirements to obtain and keep the Fiber Optic or Coaxial Cable Exemption:

  • With some exceptions, fiber optic or coaxial cable that is installed and placed in service on or after July 1, 2021 is exempt from taxation for a period of 5 years.
  • After the initial five-year period, the property exemption is phased out at a rate of 20% a year. The property will be assessed at 100% of its taxable value in the 10th year after placing the cable in service. 
  • To keep the exemption, the owner of fiber optic or coaxial cable must reinvest the tax savings from the exemption by installing and placing in service new fiber optic or coaxial cable in Montana within 2 years from the date the owner first claimed the exemption, but without charging those costs to the consumer. 
  • The cost of installing or placing into service fiber optic or coaxial cable with the reinvested tax savings (without charging those costs to the consumer) must be equal to or greater than the value of the tax savings received from the tax incentive. 
  • Fiber optic or coaxial cable installed using federal funds from the American Rescue Plan Act is not eligible for exemption from taxation under this section. 

Accounting details for the exemption:

  • An entity that claims this tax exemption shall maintain adequate books and records proving the investment made by the owner during installation and placement into service of the fiber optic or coaxial cable in Montana. These records must be available to the department for inspection upon request. 
  • The property taxes exempted from taxation are subject to termination or recapture if the department determines that the owner failed to install and place in service new coaxial or fiber cable in Montana as described the provisions of Senate Bill (SB) 51.
  • If the department notifies the owner that their exemption has terminated, any local governing body may recapture taxes previously exempted in that jurisdiction, plus interest and penalties for nonpayment of property taxes. Tax recapture must occur within 10 years after the end of the calendar year in which the exemption was first claimed. 
  • The recapture of abated taxes may be canceled, in whole or in part, if the local governing body determines that the taxpayer’s failure to meet the requirements is a result of circumstances beyond the control of the taxpayer. 

For the precise details and citations of SB 51, we invite you to read the full bill.

Please complete the form below to begin the process to obtain your fiber optic or coaxial cable exemption. 

Fields marked with an * are required

View all current Fiber Optic or Coaxial Cable Exemptions below.
Company # Company Project Description Date Received Location City if applicable Start Date Estimated Completion Date Estimated Investment Date County Commissioners Notified Commissioner Comments
503 InterBel Extension of requested mainline services and associated electronics required to get fiber to the premise. 3/13/2023 Flathead Olney, 1/1/2022 12/31/2022 $849,406 8/29/2023 None
503 InterBel FTTH Extension in North Lincoln County. 3/13/2023 Lincoln Eureka, Rexford,
Fortine, and Trego
1/1/2022 12/31/2022 $713,602 8/29/2024 None
NA Bozeman Fiber d/b/a Yellowstone Fiber A 15 Phase project with the intent to cover a majority of the home and businesses in Bozeman with individual fiber optic connections. In 2022 areas BZ015 and BZ011A were completed and lit. In 2023 we intend to address and complete 6 more areas, with the possibility of it being up to 8 areas. Then in 2024 we will complete the remaining areas as funding allows. This will be a redundant network with 250/250 Mbps, 1 gig and up to 10 gig service to every available residence or building. 100 Gig would be possible with the acquisition of additional electronic equipment in our huts. As a C-3 we will be able too, and will deliver low cost broadband services through our open network service providers. Tis is being done with private equity investment money, not tax payer based funding. 3/10/2023 Gallatin Bozeman 9/30/2023 3/15/2025 $65,000,000 8/29/2023 None
515 Northern Telephone Coop 2022 FTTH Projects 3/23/2023 Liberty, Toole NA 6/21/2021 10/31/2022 $1,088,000 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Carter NA 1/1/2022 11/30/2022 $8,535.95 8/29/2024 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Custer NA 10/1/2021 10/31/2022 $4,677.40 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Dawson NA 1/1/2020 12/31/2022 $5,348,820.15 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Fallon NA 10/31/2021 8/31/2022 $4,585.32 8/29/2024 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Fergus NA 9/30/2020 12/31/2022 $35,805.64 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Garfield NA 9/30/2021 11/30/2022 $15,200.48 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Golden Valley NA 11/30/2020 12/31/2022 $31,277.26 8/29/2024 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 McCone NA 2/28/2021 12/31/2022 $3,779,411.96 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Musselshell NA 7/1/2020 12/31/2022 $77,071.23 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Petroleum NA 4/1/2022 12/31/2022 $27,143.73 8/29/2024 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Prairie NA 7/1/2021 8/31/2022 $3,930.09 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Richland NA 2/1/2021 11/30/2022 $5,703,778.48 8/29/2023 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Wibaux NA 4/1/2020 4/30/2022 $21,715.16 8/29/2024 None
505 Mid Rivers Fiber Optic & Coaxial Installation to Customers 3/31/2023 Yellowstone NA 8/1/2021 12/31/2022 $8,238.93 8/29/2023 None
328 TDS Metro TDS Metrocom, LLC is in the process of making significant fiber optic investments throughout the state of Montana in multiple cities and counties. This is a multi year investment plan with the majority of the fiber optic network remaining in construction phase. At year end 2022 a portion of the network in Billings, MT is in service and operational. This exemption claim is for that operational portion in Billings. 3/30/2023 Yellowstone Billings 7/1/2021 12/1/2022 $2,629,796 8/29/2023 None
520 Range Telephone Fiber Optic Installation to Customers 3/29/2023 Treasure NA 1/1/2021 12/31/2022 $1,706,331 8/29/2023 None
520 Range Telephone Fiber Optic Installation to Customers 3/29/2023 Powder River NA
520 Range Telephone Fiber Optic Installation to Customers 3/29/2023 Carter NA
520 Range Telephone Fiber Optic Installation to Customers 3/29/2023 Custer NA
520 Range Telephone Fiber Optic Installation to Customers 3/29/2023 Big Horn NA
520 Range Telephone Fiber Optic Installation to Customers 3/29/2023 Rosebud NA
NA Bialecki Holdings Fiber installation Cascade County 2/13/2024 Cascade NA 12/1/2020 7/31/2023 $1,500,000 2/20/2024 None
NA Bozeman Fiber DBA Yellowstone Fiber Fiber optic cable placement aerially and underground in most areas of Bozeman Montana. Includes "Huts" for electronics. This is state of the art Ethernet type connections to supply up to 10Gig per home at prices everyone can afford. Will enhance work from home, student studies, gaming, security, business operations and any other use requiring highly reliable and fast internet services. This is a street-by-street project, with Construction starting in 2022 and ending (other than street to home) in late 2025 (weather is a factor in timing). 3/13/2024 Gallatin Bozeman 1/1/2022 12/31/2025 $49,500,000 4/1/2024 None
503 InterBel Telephone Coop FTTP construction as a result of line extension request for both single use
and subdivision developments.
3/13/2024 Flathead NA 1/1/2023 12/31/2023 $639,126 4/2/2024 None
503 InterBel Telephone Coop FTTP construction as a result of line extension request for both single use
and subdivision developments.
3/13/2024 Lincoln NA 1/1/2023 12/31/2023 $1,399,065 4/2/2024 None
515 Northern Telephone Coop Fiber Optic Installations 3/27/2024 Toole, Liberty, and Glacier NA 5/1/2022 12/31/2023 $113,535 4/2/2024 None
520 Range Telephone Coop NORTH BROADUS FTTH (10ONB2001) and N BROADUS PH 4&5 FTTH 4/2/2024 Custer and Powder River NA 4/1/2022 12/31/2023 $5,991,782 4/9/2024 None
330 Grizzly Broadband, LLC Install buried fiber optic cabling in Ravalli County, Montana. Rural Montana is going to receive high-speed internet to assist local residents and expand opportunities for current and future businesses. The project began late 2022 and was finished by the end of 2023 for this phase. 4/10/2024 Ravalli NA 1/1/2023 12/31/2023 $3,288,057 4/16/2024 See Attachment
340 SOUTHERN MONTANA TELEPHONE Install buried fiber optic cabling in Jackson, and Grant Montana. Rural Montana is going to receive high-speed internet to assist local ranchers, expand opportunities for current and future businesses, help students find solutions to their homework assignments, and allow consumers to purchase necessities. The majority of the project was operating in December, 2021, but the final project will not be complete until December 2022. 6/28/2022 BEAVERHEAD JACKSON AND GRANT 3/3/2020 12/1/2022 $1,366,864 July 27-29, 2022 No comments received to date.
322 TRI COUNTY TELEPHONE Warren to Billings Fiber 3/10/2022 BIG HORN 1/1/2018 12/31/2022 $4,900,000 July 27-29, 2022 No comments received to date.
322 TRI COUNTY TELEPHONE Warren to Billings Fiber 3/10/2022 CARBON 1/1/2018 12/31/2022 $4,900,000 July 27-29, 2022 No comments received to date.
JOSEPH'S HANDYMAN SERVICE Running fiber from closet node to business for internet Access 4/3/2022 CASCADE GREAT FALLS 5/1/2022 6/1/2022 $2,000 July 27-29, 2022 No comments received to date.
503 InterBel TELEPHONE COOP Olney to Kalispell Transport 3/21/2022 FLATHEAD OLNEY AND KALISPELL 7/1/2021 3/31/2022 $2,258,425 July 27-29, 2022 No comments received to date.
503 InterBel TELEPHONE COOP InterBel Telephone Cooperative 2021 FTTH Modernization - USDA RUS Loan project
InterBel Telephone Cooperative, Inc. 2021 Fiber to the Premise
3/23/2022 LINCOLN EUREKA 7/1/2021 12/31/2021 $1,188,201
$855,957
July 27-29, 2022 No comments received to date.
306 NORTHWEST FIBER LLC DBA ZIPLY NW Fiber purchased Frontier and is laying new fiber in Lincoln County. 6/21/2022 LINCOLN 7/31/2021 12/31/2022 $13,206,000 July 27-29, 2022 No comments received to date
341 BLACKFOOT COMMUNICATIONS Fiber Optic Cable Installation 6/16/2022 GALLATIN, MISSOULA 7/1/2021 12/31/2021 $835,958 July 27-29, 2022 No comments received to date.
500 BLACKFOOT TELEPHONE COOP Fiber Optic Cable Installation 6/16/2022 MISSOULA, LAKE, POWELL, SANDERS 7/1/2021 12/31/2021 $9,010,284 July 27-29, 2022 No comments received to date.
346 CHARTER COMMUNICATIONS Fiber and Coaxial Cable Expansion 3/30/2022 BEAVERHEAD, BROADWATER, CARBON, DEER LODGE, HILL, FLATHEAD, GALLATIN, JEFFERSON,LAKE, LEWIS & CLARK, MISSOULA, PARK, PHILLIPS, RAVALLI, SILVER BOW, STILLWATER, YELLOWSTONE 7/1/2021 12/31/2021 $8,368,323 July 27-29, 2022 No comments received to date.
505 MID RIVERS TELEPHONE COOP Fiber Optic Installation to Customers 4/1/2022 BIG HORN, CARTER, CUSTER, DAWSON, FALLON, FERGUS, GARFIELD, GOLDEN VALLEY, MCCONE, MUSSELLSHELL, PETROLEUM, RICHLAND, ROSEBUD, WHEATLAND, WIBAUX, YELLOWSTONE 7/1/2021 12/1/2022 $23,745,493 July 27-29, 2022 No comments received to date.
515 NORTHERN TELEPHONE COOP Northern Telephone Cooperative, Inc. is working to upgrade its facilities from copper to fiber to each of its members. Fiber to the home (FTTH) has been our focus for the last several years; the 2021 construction season included work in the Town of Kevin and several smaller projects in our rural service area. Work will continue in the Town of Kevin and then move to the Town of Sunburst, while also working on smaller construction requests as these come in from members. 4/1/2022 TOOLE KEVIN AND SUNBURST 1/1/2022 7/1/2023 2.5-3 MILLION July 27-29, 2022 No comments received to date.
322 TRI COUNTY TELEPHONE Warren to Billings Fiber 3/10/2022 YELLOWSTONE 1/1/2018 12/31/2022 $4,900,000 July 27-29, 2022 No comments received to date.